THE MOST IMPORTANT DATES:
19.01.2009: Opening of the call for applications for projects in the framework of Priority 2: “Environment and Infrastructure” of the Swiss-Polish Cooperation Programme (thematic area: “Rehabilitation and modernization of basic infrastructure and improvement of the environment”, Objective 3: To improve the management, the safety, the efficiency and the reliability of communal/regional public transportation systems (transport)
20.03.2009: Submission of the Project Outline to the Intermediate Body by WKD
30.09.2010: Submission of the Full Project Proposal to the Intermediate Body by WKD
21.11.2011: Approval of the WKD’s Full Project Proposal by the Swiss State Secretariat for Economic Affairs (SECO)
26.06.2012: Signing of the Agreement concerning the Project Realization between the Intermediate Body (the Implementation Authority for European Programmes – presently Digital Poland Project Centre) and Warszawska Kolej Dojazdowa sp. z o.o.
26.08.2014: Signing of the Agreement concerning the delivery of 6 electric multiple units
15.09.2014: Signing of the Agreement concerning the construction of automatic signalling system devices at 8 railway crossings of the WKD railway
24.03.2015: Signing of an amendment to the Agreement concerning the Project Realization which added a new investment undertaking
18.08.2015: Signing of the Agreement concerning the construction of Passenger Information and Monitoring System
05.01.2016: Announcement of the contest for the creation of an architectural concept of street furniture for WKD platforms
28.02.2016: Entry into service of the constructed automatic signalling system devices at 8 railway crossings
18.03.2016: Signing of the Agreement concerning the comprehensive repair of track No. 2 on the Warszawa Sródmieście WKD – Komorów railway route
19.04.2016: The announcement of the results of the contest for the creation of an architectural concept of street furniture for WKD platforms
29.04.2016: Commencement of the delivery of 6 electric multiple units
01.06.2016: Signing of the Agreement concerning the construction of automatic signalling system devices at another 8 facilities
01.07.2016: Commencement of the comprehensive repair of track No. 2 on the Warszawa Sródmieście WKD – Komorów railway route
05.08.2016: Signing of the Agreement concerning the modernisation of track No. 1 on the Komorów – Podkowa Leśna Główna railway route and the track No 1M on the Podkowa Leśna Główna – Milanówek Grudów railway route
22.08.2016: Conclusion of the delivery of 6 electric multiple units
31.08.2016: Conclusion of the comprehensive repair of track No. 2 on the Warszawa Sródmieście WKD – Komorów railway route
15.09.2016: Commencement of the modernisation of track No. 1 on the Komorów – Podkowa Leśna Główna railway route and the track No. 1M on the Podkowa Leśna Główna – Milanówek Grudów railway route
31.10.2016: Conclusion of the modernisation of track No. 1 on the Komorów – Podkowa Leśna Główna railway route and the track No. 1M on the Podkowa Leśna Główna – Milanówek Grudów railway route
17.11.2016: Signing of the Agreement concerning the delivery and assembly of a new raised platform for servicing electric multiple units
27.02.2017: Entry into service of the constructed automatic signalling system devices at 8 railway crossings
28.02.2017: Entry into service of Passenger Information and Monitoring System after the period of production supervision
31.05.2017: Conclusion of the implementation of the Project