THE MOST IMPORTANT DATES:

19.01.2009: Opening of the call for applications for projects in the framework of Priority 2: “Environment and Infrastructure” of the Swiss-Polish Cooperation Programme (thematic area: “Rehabilitation and modernization of basic infrastructure and improvement of the environment”, Objective 3: To improve the management, the safety, the efficiency and the reliability of communal/regional public transportation systems (transport)

20.03.2009: Submission of the Project Outline to the Intermediate Body by WKD

30.09.2010: Submission of the Full Project Proposal to the Intermediate Body by WKD

21.11.2011: Approval of the WKD’s Full Project Proposal by the Swiss State Secretariat for Economic Affairs (SECO)

26.06.2012: Signing of the Agreement concerning the Project Realization between the Intermediate Body (the Implementation Authority for European Programmes – presently Digital Poland Project Centre) and Warszawska Kolej Dojazdowa sp. z o.o.

26.08.2014: Signing of the Agreement concerning the delivery of 6 electric multiple units

15.09.2014: Signing of the Agreement concerning the construction of automatic signalling system devices at 8 railway crossings of the WKD railway

24.03.2015: Signing of an amendment to the Agreement concerning the Project Realization which added a new investment undertaking

18.08.2015: Signing of the Agreement concerning the construction of Passenger Information and Monitoring System

05.01.2016: Announcement of the contest for the creation of an architectural concept of street furniture for WKD platforms

28.02.2016: Entry into service of the constructed automatic signalling system devices at 8 railway crossings

18.03.2016: Signing of the Agreement concerning the comprehensive repair of track No. 2 on the Warszawa Sródmieście WKD – Komorów railway route

19.04.2016: The announcement of the results of the contest for the creation of an architectural concept of street furniture for WKD platforms

29.04.2016: Commencement of the delivery of 6 electric multiple units

01.06.2016: Signing of the Agreement concerning the construction of automatic signalling system devices at another 8 facilities

01.07.2016: Commencement of the comprehensive repair of track No. 2 on the Warszawa Sródmieście WKD – Komorów railway route

05.08.2016: Signing of the Agreement concerning the modernisation of track No. 1 on the Komorów – Podkowa Leśna Główna railway route and the track No 1M on the Podkowa Leśna Główna – Milanówek Grudów railway route

22.08.2016: Conclusion of the delivery of 6 electric multiple units

31.08.2016: Conclusion of the comprehensive repair of track No. 2 on the Warszawa Sródmieście WKD – Komorów railway route

15.09.2016: Commencement of the modernisation of track No. 1 on the Komorów – Podkowa Leśna Główna railway route and the track No. 1M on the Podkowa Leśna Główna – Milanówek Grudów railway route

31.10.2016: Conclusion of the modernisation of track No. 1 on the Komorów – Podkowa Leśna Główna railway route and the track No. 1M on the Podkowa Leśna Główna – Milanówek Grudów railway route

17.11.2016: Signing of the Agreement concerning the delivery and assembly of a new raised platform for servicing electric multiple units

27.02.2017: Entry into service of the constructed automatic signalling system devices at 8 railway crossings

28.02.2017: Entry into service of Passenger Information and Monitoring System after the period of production supervision

31.05.2017: Conclusion of the implementation of the Project

Quick Contact

Warsaw Commuter Railway Sp. z o.o.
UL. BATOREGO 23
05-825 GRODZISK MAZOWIECKI
TEL. (22) 755-55-64
FAX (22) 755-20-85



Useful Links

Szwajcarsko-Polski Program Współpracy
www.programszwajcarski.gov.pl
www.swiss-contribution.admin.ch 

Ministerstwo Infrastruktury i Rozwoju
www.mr.gov.pl

Centrum Projektów Polska Cyfrowa
www.cppc.gov.pl